Saturday, April 18, 2009


It is four weeks to the day until our first clients arrive all the way from Winnepeg, Canada.Now the pressure is really on! The pool house is advancing, Thijs and his crew worked all day today,Saturday, but we are really up against it. We have to have the rendering of the pool finished by Tuesday so that we can order the cover, this is likely to take at least two weeks to come and only then can we start putting water in the pool! So at worst the pool may not be full and at best it will be but cold! There is also the decking to be done all around the pool, further landscaping to conceal the parking area , oh yes and of course Le Chene, Karen and I are now on cleaning, snagging, putting up lights , curtains, bathroom fitments, door handles etc and then there is the garden at Les cypres before our next guests arrive there. And yet another storm rolls in! just what we do not need!